Item details
Designated Exempted Works item no. | 19 |
---|---|
Nature of works | Erection/Alteration/Repair/Removal of any pole on a roof of a building |
Result in any additional load to any cantilevered slab | No |
The works involve alteration of any other structural elements | No |
The height of the pole, including any feature at its top | Not more than 1.1 m |
If there is no protective barrier with a height of not less than 1.1 m at any edge of the roof, the distance between any part of the pole and that edge | More than 1.5 m |
For erection or alteration works—if there is more than 1 pole on the roof, the distance between the poles | At least 2.5 m away from each other |
More details: See Item 19 Description of building works, Schedule 2 - Part 2, Building (Minor Works) Regulation