Item details
Item no. | 1.26 |
---|---|
Item class/type | Class I TypeD |
Nature of works | Addition/Alteration |
Excavation depth | More than 1.5m but not more than 3m |
The distance between any point of the excavation and the bottom of any retaining wall or the toe of any slope with a gradient of more than 15 degrees | At least equal to the depth of the excavation |
The works involve the last manhole | No |
If the works are carried out beside the crest of a slope with a gradient of the slope is not more than 15 degrees |
|
If the works are carried out beside the top of a retaining wall |
|
More details: See Item 1.26 Description of building works, Schedule 1 - Part 3 - Division 1, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint Prescribed Building Professional and Prescribed Registered Contractor (Class I of Type D)
Step 2
Prescribed Building Professionals
Submit MW01 - Notice of Commencement, documents, photos 7 days before commencement of work
Step 3
Prescribed Building Professionals
Submit MW02 - Certificate of Completion, documents, photos within 14 days after completion of work