Minor works items - 1.46
Class I TypeAEH
- Jump to
- Item details
- Submission procedure
Item details
Item no. | 1.46 |
---|---|
Item class/type | Class I TypeAEH |
Nature of works | Erection/Alteration |
Location of the ventilation duct or any associated supporting structure | Inside a building |
Result in any additional load to any cantilevered slab | No |
The smallest cross-sectional dimensions of the duct | More than 900mm |
The largest cross-sectional dimensions of the duct | More than 1800mm |
More details: See Item 1.46 Description of building works, Schedule 1 - Part 3 - Division 1, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint Prescribed Building Professional and Prescribed Registered Contractor (Class I of Type A, E, H)
Step 2
Prescribed Building Professionals
Submit MW01 - Notice of Commencement, documents, photos 7 days before commencement of work
Step 3
Prescribed Building Professionals
Submit MW02 - Certificate of Completion, documents, photos within 14 days after completion of work