Minor works items - 2.20
- Jump to
- Item details
- Submission procedure
Item details
Item no. | 2.20 |
---|---|
Item class/type | Class II TypeC |
Nature of works | Erection/Alteration |
The works related to cantilevered slab balcony or canopy | No |
Location of the signboard | Located on or hung underneath the soffit of a balcony (other than a cantilevered slab) or canopy (other than a cantilevered slab) |
The signboard consist of stone | No |
The display area of the signboard | Not more than 2m2 |
The signboard projects beyond the balcony or canopy | No |
The height of the signboard | Not more than 600mm |
The thickness of the signboard | Not more than 100mm |
More details: See Item 2.20 Description of building works, Schedule 1 - Part 3 - Division 2, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint Prescribed Registered Contractor (Class II of Type C)
Step 2
Prescribed Registered Contractors
Submit MW03 - Notice of Commencement, documents, photos 7 days before commencement of work
Step 3
Prescribed Registered Contractors
Submit MW04 - Certificate of Completion, documents, photos within 14 days after completion of work