Minor works items - 2.29
- Jump to
- Item details
- Submission procedure
Item details
Item no. | 2.29 |
---|---|
Item class/type | Class II TypeD |
Nature of works | Addition/Alteration |
Excavation depth | Not more than 1.5m |
The distance between any point of the excavation and the bottom of any retaining wall or the toe of any slope with a gradient of more than 15 degrees | At least equal to the depth of the excavation |
The works involve the last manhole | No |
If the works are carried out beside the crest of a slope with a gradient of the slope is not more than 15 degrees |
|
If the works are carried out beside the top of a retaining wall |
|
More details: See Item 2.29 Description of building works, Schedule 1 - Part 3 - Division 2, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint Prescribed Registered Contractor (Class II of Type D)
Step 2
Prescribed Registered Contractors
Submit MW03 - Notice of Commencement, documents, photos 7 days before commencement of work
Step 3
Prescribed Registered Contractors
Submit MW04 - Certificate of Completion, documents, photos within 14 days after completion of work