Minor works items - 2.30
- Jump to
- Item details
- Submission procedure
Item details
Item no. | 2.30 |
---|---|
Item class/type | Class II TypeD |
Nature of works | Erection/Repair/Alteration/Removal |
Scope of works | The works involve any aboveground drain |
The works involve main pipe | Yes |
Result in any additional load to any cantilevered slab | No |
The works involve the repair or replacement of an internal branch pipe or sanitary fitment | No |
Other requirement | Not involve Minor Works item 3.23 |
More details: See Item 2.30 Description of building works, Schedule 1 - Part 3 - Division 2, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint Prescribed Registered Contractor (Class II of Type D)
Step 2
Prescribed Registered Contractors
Submit MW03 - Notice of Commencement, documents, photos 7 days before commencement of work
Step 3
Prescribed Registered Contractors
Submit MW04 - Certificate of Completion, documents, photos within 14 days after completion of work