Minor works items - 2.31
Class II TypeAEG
- Jump to
- Item details
- Submission procedure
Item details
Item no. | 2.31 |
---|---|
Item class/type | Class II TypeAEG |
Nature of works | Removal |
Scope of works | The works involve supporting frame for an air-conditioning unit, light fittings, antenna or transceiver for public telecommunications services, or any rack (other than a drying rack) |
Location of the supporting frame | Projecting from the external wall of a building or a fence wall |
Projection from the wall | More than 750mm |
Constructed of concrete | No |
More details: See Item 2.31 Description of building works, Schedule 1 - Part 3 - Division 2, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint Prescribed Registered Contractor (Class II of Type A, E, G)
Step 2
Prescribed Registered Contractors
Submit MW03 - Notice of Commencement, documents, photos 7 days before commencement of work
Step 3
Prescribed Registered Contractors
Submit MW04 - Certificate of Completion, documents, photos within 14 days after completion of work