Minor Works Item - 2.45

Minor works items - 2.45

Class II TypeA
Category
Trellises
Forms
MW03 MW04

Item details

Minor Works Item - 2.45
Item no. 2.45
Item class/type Class II TypeA
Nature of works Erection/Alteration/Removal
Location of the trellis Located on a roof of a building
Result in any additional load to any cantilevered slab No
The works involve the alteration of any other structural elements No
Height of the trellis Not more than 2.5m

For erection or alteration

The length and width of every opening of the overhead framework of the trellis Not less than 200mm
The horizontal clearance of the trellis from any other structure Not less than 500 mm
For works carried out in a common part of the building and at the completion of the works
  1. Each trellis located in that common part covers an area of not more than 5m2; and
  2. The aggregate of the area covered by each trellis located in that common part is not more than 5% of the total area of that part
For works carried out in a part that is not a common part of the building (non-common part) and at the completion of the works
  1. Each trellis located in that non-common part covers an area of not more than 5m2; and
  2. The aggregate of the area covered by each trellis located in that non-common part is not more than 20m2 and not more than 5% of the total area of that part

For removal

The area covered by the trellis Not more than 20m2

Submission procedure

Owner or their agent

Appoint Prescribed Registered Contractor (Class II of Type A)

Search for Eligible Professionals/Contractors online

Prescribed Registered Contractors

Submit MW03 - Notice of Commencement, documents, photos 7 days before commencement of work

MW03 formSee sample

Prescribed Registered Contractors

Submit MW04 - Certificate of Completion, documents, photos within 14 days after completion of work

MW04 formSee sample