Minor works items - 2.8
- Jump to
- Item details
- Submission procedure
Item details
Item no. | 2.8 |
---|---|
Item class/type | Class II TypeA |
Nature of works | Construction/Alteration/Repair/Replacement |
Scope of works | The works involve windows or window walls |
Result in any additional load to any cantilevered slab | No |
Span of structural element of the window or window wall | Not more than 6m |
The works involve the alteration of any other structural elements (except a simply supported beam that -
|
No |
For Construction or Alteration |
|
If the distance between the highest point of the window or window wall and the ground is more than 3.5m but not more than 100m |
|
If the distance between the highest point of the window or window wall and the ground is more than 100m |
|
For Repair or Replacement |
|
If the distance between the highest point of the window or window wall and the ground is more than 3.5m but not more than 100m |
|
If the distance between the highest point of the window or window wall and the ground is more than 100m |
|
More details: See Item 2.8 Description of building works, Schedule 1 - Part 3 - Division 2, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint Prescribed Registered Contractor (Class II of Type A)
Step 2
Prescribed Registered Contractors
Submit MW03 - Notice of Commencement, documents, photos 7 days before commencement of work
Step 3
Prescribed Registered Contractors
Submit MW04 - Certificate of Completion, documents, photos within 14 days after completion of work