Item no. | 2.9 |
---|---|
Item class/type | Class II TypeAG |
Nature of works | Removal |
Scope of works | The works involve windows or window walls |
The works involve any structural alteration | No |
The distance between the highest point of the window or window wall and the ground | More than 3.5m |
The height of the window or window wall | Not more than 6m |
Other Requirement | Not involve Minor Works item 3.7 |
More details: See Item 2.9 Description of building works, Schedule 1 - Part 3 - Division 2, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint Prescribed Registered Contractor (Class II of Type A, G)
Step 2
Prescribed Registered Contractors
Submit MW03 - Notice of Commencement, documents, photos 7 days before commencement of work
Step 3
Prescribed Registered Contractors
Submit MW04 - Certificate of Completion, documents, photos within 14 days after completion of work