Minor works items - 3.21
- Jump to
- Item details
- Submission procedure
Item details
Item no. | 3.21 |
---|---|
Item class/type | Class III TypeCG |
Nature of works | Removal |
Scope of works | Located on or hung underneath the soffit of a balcony (other than a cantilevered slab) or canopy (other than a cantilevered slab) |
If located on a balcony or canopy, the display area of the signboard | Not more than 5m2 |
If hung underneath the soffit of a balcony or canopy, the display area of the signboard | Not more than 2m2 |
The height of the signboard | Not more than 1m |
More details: See Item 3.21 Description of building works, Schedule 1 - Part 3 - Division 3, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint and Prescribed Registered Contractor (Class III of Type C, G)
Step 2
Prescribed Registered Contractors
Submit MW05 - Notice of Commencement, documents, photos within 14 days after completion of work