Minor works items - 3.37
- Jump to
- Item details
- Submission procedure
Item details
Item no. | 3.37 |
---|---|
Item class/type | Class III TypeAE |
Nature of works | Strengthening |
Scope of works | Any unauthorised canopy projecting from the external wall of a building |
Result in any additional load to any cantilevered slab | No |
Projection from the wall | Not more than 500 mm |
Constructed of concrete | No |
If the distance between the highest point of the canopy and the ground is not more than 3m | The canopy cannot project over any street or common part of the building. |
More details: See Item 3.37 Description of building works, Schedule 1 - Part 3 - Division 3, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint and Prescribed Registered Contractor (Class III of Type A, E)
Step 2
Prescribed Registered Contractors
Submit MW05 - Notice of Commencement, documents, photos within 14 days after completion of work