Minor Works Items

Removal of other structures (chimneys/architectural projections/racks)

Contractors can only undertake the relevant classes or items of minor works for which they have been registered.

Removal of chimneys

Removal
Class I

1.37

Minor Works Items 1.37

Removal

  1. The chimney attached to the external wall of a building or located on the roof of a building
  2. Highest point of the chimney and the level of the adjoining roof
    ≤ 10m
Class II

2.37

Minor Works Items 2.37

Removal

  1. The chimney attached to the external wall of a building or located on the roof of a building
  2. Highest point of the chimney and the level of the adjoining roof
    ≤ 5m
  3. Smallest cross-sectional dimension of the chimney
    ≤ 500mm

Removal of architectural projections or racks (other than drying racks)

Removal
Class II

2.31

Minor Works Items 2.31

Removal

  1. Projecting from the external wall
    > 750mm
Class III

3.26

Minor Works Items 3.26

Removal

  1. Projecting from the external wall
    ≤ 750mm
Top