Item details
Item no. | 2.2 |
---|---|
Item class/type | Class II TypeAEG |
Nature of works | Removal |
Location of the supporting structure for a building service installation or any metal casing for such an installation |
|
The height of the structure | Any |
Other requirement | Not involve Designated Exempted Works item 12 or Minor Works item 3.2 |
More details: See Item 2.2 Description of building works, Schedule 1 - Part 3 - Division 2, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint Prescribed Registered Contractor (Class II of Type A, E, G)
Step 2
Prescribed Registered Contractors
Submit MW03 - Notice of Commencement, documents, photos 7 days before commencement of work
Step 3
Prescribed Registered Contractors
Submit MW04 - Certificate of Completion, documents, photos within 14 days after completion of work