Item no. | 3.36 |
---|---|
Item class/type | Class III TypeAE |
Nature of works | Strengthening |
Scope of works | Any unauthorised drying rack projecting from the external wall of a building |
Result in any additional load to any cantilevered slab | No |
Projection from the wall | Not more than 750mm |
If the distance between the highest point of the rack and the ground is not more than 3m | The rack does cannot project over any street or common part of the building |
More details: See Item 3.36 Description of building works, Schedule 1 - Part 3 - Division 3, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint and Prescribed Registered Contractor (Class III of Type A, E)
Step 2
Prescribed Registered Contractors
Submit MW05 - Notice of Commencement, documents, photos within 14 days after completion of work