Minor works items - 3.48
- Jump to
- Item details
- Submission procedure
Item details
Item no. | 3.48 |
---|---|
Item class/type | Class III TypeAE |
Nature of works | Erection/Alteration |
Location of the external metal ventilation duct or associated supporting frame |
|
Result in any additional load to any cantilevered slab | No |
If the duct or frame projects from the external wall of a building |
|
If the duct or frame is located on a balcony, verandah or canopy |
|
If the duct or frame is hung underneath the soffit of a balcony, verandah or canopy |
|
More details: See Item 3.48 Description of building works, Schedule 1 - Part 3 - Division 3, Building (Minor Works) Regulation
Submission procedure
Step 1
Owner or their agent
Appoint and Prescribed Registered Contractor (Class III of Type A, E)
Step 2
Prescribed Registered Contractors
Submit MW05 - Notice of Commencement, documents, photos within 14 days after completion of work